Project Resource Management – PMBOK Sixth Edition

Project Management Body of Knowledge

Introduction

Project Resource management has gone through major changes. Some of them were big gaps in earlier editions and some of them were logically moved from project schedule management knowledge area. The below tables show at a high level these changes

Knowledge area level name change

5TH EDITION

6TH EDITION

REMARKS

Project HR Management

Project Resource Management

Both team and physical resources such as materials, equipment are managed in the 6th edition

Process level changes and additions

KNOWLEDGE AREA

PROCESS

CHANGE

Project Schedule Management

Estimate Activity Resources

Moved to Project Resources Management

Project Resources Management

Control Resources

Added

Process level name changes

KNOWLEDGE AREA

PROCESS NAME - OLD

PROCESS NAME - NEW

REASON

Project Resources Management

1. Plan Human Resource Management
2. Acquire Project team
3. Develop Project Team
4. Manage Project Team

1. Plan Resource Management
2. Acquire resources
3. Develop team
4. Manage Team
5. Control Resources

1. All types of resources are planned
2. All types of resources are acquired

The total number of processes now become 6

FIFTH EDITION PROCESSES

SIXTH EDITION PROCESSES

9.1 Plan Human Resource Management

9.1 Plan Resource Management

9.2 Acquire Project Team

9.2 Estimate Activity Resources

9.3 Develop Project Team

9.3 Acquire Resources

9.4 Manage Project Team

9.4 Develop Team


9.5 Manage Team

9.6 Control Resources

Trends and  Emerging Practices in Project Schedule Management

The following emerging trends and practices have been introduced in project resource management

  • Resource Management methods
    • Lean, JIT, Kaizen, TPM, TOC etc.
  • Emotional intelligence
    • Personal EI (inbound – Self-awareness, self-management, and outbound – Relationship management)
    • Team EI (emotionally competent team )
  • Self-organizing teams
    • Agile world
  • Virtual teams and distributed teams

ITTO Changes across the Processes

Plan Resource Management Plan :

The process now includes team and physical resources. The definition goes as below.

The process of defining how to estimate, acquire, manage and use team and physical resources.

Resource planning is done looking at the requirements, scope/deliverables, schedule for timeline, quality and risk to choose the right caliber of resources

Team charter that speaks about the team values, communication guidelines, agreements etc is a new addtion to this version

INPUT

T&T

OUTPUT

Project charter

Expert judgment

Resource management plan

Project management plan
1. Quality management plan
2. Scope baseline

Data representation
1. Hierarchical charts
2. Responsibility assignment matrix
3. Text-oriented formats

Team charter

Project documents
1. Project schedule
2. Requirements documentation
3. Risk register
4. Stakeholder register

Organizational theory

Project documents updates
1. Assumption log
2. Risk register

EEF & OPA

Meetings

Estimate Activity Resources

This process has been moved from Project Schedule Management.

The activities and attributes for estimation comes from schedule management, how to estimate comes from resource management plan. Cost estimates comes as additional input to balance resource estimates with cost estimates. Analogues and parametric estimating methods are added

INPUT

T&T

OUTPUT

Project management plan
1. Resource management plan
2. Scope baseline

Expert judgment

Activity Resource requirements

Project documents
1. Activity attributes
2. Activity list
3. Assumption log
4. Cost estimates
5. Resource calendars
6. Risk register

Bottom-up estimating

Basis of estimates

EEF & OPA

Analogous estimating

Resource breakdown structure

Parametric estimating

Project documents updates
1. Activity attributes
2. Assumption log
3. Lessons learned register

Data analysis
1. Alternatives analysis

Project management information system

Meetings

Acquire Resources

Acquisition technique removed as this would be handled as part of procurement. Procurement management plan will be updated with this effect. Output includes physical resource assignments

Additional stakeholders will come in and hence it is added as input and updates as output

[

INPUT

T&T

OUTPUT

Project management plan
1. Resource management plan
2. Procurement management plan
3. Cost baseline

Decision making
1. Multi criteria decision analysis

Physical resource assignments

Project documents
1. Project schedule
2. Resource calendars
3. Resource requirements
4. Stakeholder register

Interpersonal and team skills
1. Negotiation

Project team assignments

EEF & OPA

Pre-assignment

Resource calendars

Virtual teams

Change requests

Project management plan updates
1. Resource management plan
2. Cost baseline

Project documents updates
1. Lessons learned register
2. Project schedule
3. Resource breakdown structure
4. Resource requirements
5. Risk register
6. Stakeholder register

EEF & OPA updates

Develop Team

Not many changes except tools and techniques realignment

INPUT

T&T

OUTPUT

Project management plan
1. Resource management plan

Colocation

Team performance assessments

Project documents
1. Lessons learned register
2. Project schedule
3. Project team assignments
4. Resource calendars
5. Team charter

Virtual teams

Change requests

EEF & OPA

Communication technology

Project management plan updates
1. Resource management plan

Interpersonal and team skills
1. Conflict management
2. Influencing
3. Motivation
4. Negotiation
5. Team building

Project documents updates
1. Lessons learned register
2. Project schedule
3. Project team assignments
4. Resource calendars
5. Team charter

Recognition and rewards

EEF & OPA updates

Training

Individual and team assessments

Meetings

Manage Team

Not many changes except PMIS and EI are added as additional T&T

INPUT

T&T

OUTPUT

Project management plan
1. Resource management plan

Interpersonal and team skills
1. Conflict management
2. Decision making
3. Emotional intelligence
4. Influencing
5. Leadership

Change requests

Project documents
1. Issue log
2. Lessons learned register
3. Project team assignments
4. Team charter

Project management information system

Project management plan updates
1. Resource management plan
2. Schedule baseline
3. Cost baseline

Work performance reports

Project documents updates
1. Issue log
2. Lessons learned register
3. Project team assignments

Team performance assessments

EEF updates

EEF & OPA

Control Resources

This is new process. It is one of the critical challenge in real time projects. The project managers constantly perform alternative analysis, cost benefit analysis, negotiate, in fluent to keep the resources working on the tasks

Agreements is taken as input to check the commitments made to customer. Baselines, Plans and documents are updated to reflect the changes

INPUT

T&T

OUTPUT

Project management plan
1. Resource management plan

Data analysis
1. Alternatives analysis
2. Cost-benefit analysis
3. Performance reviews
4. Trend analysis

Work performance information

Project documents
1. Issue log
2. Lessons learned register
3. Physical resource assignments
4. Project schedule
5. Resource breakdown structure
6. Resource requirements
7. Risk register

Problem solving

Change requests

Work performance data

Interpersonal and team skills
1. Negotiation
2. Influencing

Project management plan updates
1. Resource management plan
2. Schedule baseline
3. Cost baseline

Agreements

Project management information system

Project documents updates
1. Assumption log
2. Issue log
3. Lessons learned register
4. Physical resource assignments
5. Resource breakdown structure
6. Risk register

OPA

Summary / Conclusion

The usual soft skill elements like leadership, team building, negotiation, influencing, conflict management, motivation etc are kept as it is and the new requirements are added.

Teaching this chapter is a bit challenge as this chapter interfaces significantly with schedule management, procurement management and other areas

As said before this area had a big gap of not addressing the physical resources and that has been bridged.